Project Awarded – Detroit Dam Tainter Gate Rehabilitation

Category Archives: News

Project Awarded – Detroit Dam Tainter Gate Rehabilitation

Northbank Civil and Marine, Inc. was recently awarded the Detroit Dam Tainter Gate Rehabilitation project for $13,075,000.

The work consists of the rehabilitation of 6 tainter/spillway gates. This includes structural strengthening the gates, full replacement of the all the gate hoist equipment, replacement of the trunnion bearing systems, and replacing the switchgear, limit switches, lighting and gate control systems. Onsite work will begin in 2019 and are scheduled to complete 3 gates per season (October 15 through January 31 annually) with the project end date in 2022.


Copyright © Northbank Civil and Marine, Inc. All Rights Reserved. WA CCB: NORTHCM850P6 / OR CCB: 208646
Sitemap | Web Design Portland By: Zimmerman Designs
Select Office:

Main Office:
360-984-3336

Area Office:
503-333-2366